1 Background............................................................ 3
2 Purpose of the DBSP.............................................. 3
3 DBSP Applicability.................................................. 7
4 DBSP Implementation............................................. 7
5 DBSP Contents...................................................... 20
6 DBSP Review Procedure....................................... 34
7 DBSP Approval....................................................... 35
8 Distribution of Approved DBSP................................ 35
9 DBSP Revisions...................................................... 36
Attachment A - Definitions.............................................. 38
Attachment B - DBSP Development Process................. 40
Attachment C - DBSP Development Checklist................ 41
Attachment D - FPD Divisional Responsibilities………….43
Attachment E - DBSP Approval Sheet..............................44
Attachment F - DBSP Contributors Identification Page....45
Detailed Table of Contents
- Background......................................................................................... 3
2 Purpose of the DBSP........................................................................... 3
3 DBSP Applicability............................................................................... 7
- DBSP Implementation......................................................................... 7
5 DBSP Contents.................................................................................... 20
5.1 Approval Sheet........................................................................ 20
5.2 DBSP Contributors Identification Page................................... 21
5.3 Design Basis Scope Definition................................................ 21
5.4 DBSP Sections......................................................................... 23
5.4.1 Purpose of Facilities.................................................. 23
5.4.2 Present Situation........................................................ 23
5.4.3 Location Analysis....................................................... 25
5.4.4 Interfaces................................................................... 26
5.4.5 Design Objectives...................................................... 27
5.4.6 General Project Design Basis.................................... 28
5.4.7 Description of Proposed Facilities.............................. 29
5.4.8 Scope Evaluation to Date........................................... 29
-
-
- Additional Study Requirements during Project Proposal.30
- Constructability and Logistical Assessment................... 31
5.4.11 As-Built Drawing Assessment...................................... 31
5.4.12 Value Engineering Study.................................... 31
5.4.13 Surplus and Excess Material.............................. 32
5.4.14 Project Schedule................................................ 32
5.4.15 Appendices......................................................... 32
6 DBSP Review Procedure.............................................................. 34
7 DBSP Approval............................................................................. 35
8 Distribution of Approved DBSP.................................................... 35
9 DBSP Revisions............................................................................ 36
Attachment A - Definitions...................................................................... 38
Attachment B - DBSP Development Process......................................... 40
Attachment C - DBSP Development Checklist........................................ 41
Attachment D - FPD Divisional Responsibilities...................................... 43
Attachment E - DBSP Approval Sheet.................................................... 44
Attachment F - DBSP Contributors Identification Page........................... 45
- Background
Corporate Management has endorsed the concept that Project Proposals for individually engineered Budget Items (BIs) will be supported by Design Basis Scoping Papers (DBSPs). Facilities Planning Department (FPD) is responsible for preparation and development of these DBSPs. Consistent with this direction, the procedures for preparing, approving and revising DBSPs contained in this document are mandatory for all organizations involved in developing capital projects, including FPD, the Proponent and the Construction Agency. |