TenStep Tip. Learn the First 50% of Earned Value Management
Learn About Earned Value Management (EVM)
(Part 1 of 2)
Have you ever been asked how far along you were on a project? Of course you have. If you do not have a valid schedule, or if you are not keeping the schedule up-to-date, you know that your answer is pretty much a guess. If you have a good schedule and you are keeping it up-to-date, you should have a sense for how much work is remaining and what the projected end-date is. But are you 50% complete? Or 90% complete? It is not always easy to know.
Earned value management (EVM) was established to remove the guess work from determining where you are in relation to your baseline schedule and budget. Using it allows a project manager to know precisely how far along he is, how much work is remaining, what the expected cost will be, and all sorts of other interesting information.
Are you using earned value on your project today? Probably not. You are not using earned value because your organization has not adopted it. Implementing earned value on your project requires a tremendous level of discipline and a common set of processes. It is hard to apply earned value one project at a time, since no one else would understand what you are doing and why. It required an organization focus.
History
Earned value has not been around for hundreds of years. In the 1960s, the US Department of Defense began to mandate the use of earned value on defense related projects. As you might expect, if the government is contracting out projects worth hundreds of millions or billions of dollars, they want project progress updates to consist of more than "we seem to be on target." Earned value calculations can provide a better sense for exactly where the project is against the baseline and provide an early warning if the trends indicate that the project would be overbudget or over its deadline.
Even though EVM can be hard to understand at first, the entire model is based on just three core values.
-
Actual cost (AC). The actual cost of work completed as of a point in time.
-
Planned Value (PV). The budgeted cost of work you planned to complete as of the same point in time.
-
Earned Value (EV). The budgeted cost of the work actually completed as of the same point in time.
Earned Value is calculated by adding up the budgeted cost of every activity that has been completed. (Remember, this is not the actual cost of the work activities. This is thebudgeted cost.) Look at the following example:
Today's Date is March 31
|
Completed Activity
|
A
|
B
|
C
|
D
|
Remaining Work
|
|
Target Date
|
March 10
|
March 15
|
March 31
|
April 5
|
July 31
|
|
Budgeted Cost
|
20
|
10
|
15
|
5
|
500
|
|
Actual Cost
|
20
|
5
|
20
|
10
|
?
|
Let's say that as of March 31 you have actually completed activity A, B, C and D. Let's calculate AC, PV and EV.
-
AC is the actual cost of the work completed. This is 55 (20 + 5 + 20 + 10).
-
PV is the budgeted cost of the work planned to be completed. This is 45 (20 + 10 + 15). Note that Activity D is not counted since it was not planned to be completed as of March 31.
-
EV is the budgeted cost of the work completed. This is 50 (20 + 10 + 15 + 5).
These three numbers seem to be interesting, but by themselves they do not tell you too much. So, we need to combine and compare the values to determine our status against schedule and budget. Sorry, but this next bit of information must wait until next week's email.
..........................................................................
Learn the fundamentals of scheduling with this e-class. This e-class introduces proven processes and techniques for building a viable schedule. Review and get a sneak peak athttp://www.tenstepstore.com/detail/4.14FundamentalsofScheduling.html |